A printing company works on three types of printing jobs,each of which could be produced on the same model printing machine.The predicted annual demands and typical order sizes are shown in the table.The company has 2000 production hours available each year and requires a 10% capacity cushion to allow for preventive maintenance,breakdowns,and other unforeseen circumstances.They have floor space for five printing machines.If the time needed to set up a printing machine to switch from one job to the next is identical for all three job types,what must their setup time be to achieve their required output? A printing company works on three types of printing jobs,each of which could be produced on the same model printing machine.The predicted annual demands and typical order sizes are shown in the table.The company has 2000 production hours available each year and requires a 10% capacity cushion to allow for preventive maintenance,breakdowns,and other unforeseen circumstances.They have floor space for five printing machines.If the time needed to set up a printing machine to switch from one job to the next is identical for all three job types,what must their setup time be to achieve their required output?

Correct Answer

verifed

verified

It can't be done;the production time req...

View Answer

A manufacturing plant is capable of producing 10 tons of product per day when it runs three shifts with no breakdowns and plenty of raw materials.Over the past week,the plant has produced an average of 7.3 tons per day because the third shift has devoted much of their time to preventive maintenance.What is the utilization of the plant?


A) 10 tons/day
B) 7) 3 tons/day
C) 137%
D) 73%

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

A capacity cushion is the amount of inventory that a firm maintains to handle sudden increases in demand or temporary loss of production capacity.

A) True
B) False

Correct Answer

verifed

verified

Output measures are used for estimating capacity requirements when product variety and process divergence are high.

A) True
B) False

Correct Answer

verifed

verified

What is a capacity cushion? Provide examples of capacity cushions in a university setting and an automotive producer.

Correct Answer

verifed

verified

The term capacity cushion refers to the ...

View Answer

Capacity planning requires a demand forecast for an extended period of time into the future.What concerns would you have regarding an extended forecast as a capacity planner?

Correct Answer

verifed

verified

Unfortunately,forecast accuracy declines...

View Answer

Use the information in Scenario 4.5.What is the pre-tax cash flow (net present value) for alternative #1 compared to the base case of doing nothing for the next five years?


A) negative pre-tax cash flow
B) more than $0 but less than $40,000
C) more than $40,000 but less than $80,000
D) more than $80,000

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

A standard work year is 2000 hours at the Luther Mill and it takes about an hour and a half to fill a customer order.The manager at the mill is always concerned about employee idle time,so he aims for a capacity cushion of two percent.Last year saw 15,000 customer orders at the mill and the manager has a new John Deere in mind as a company car,so he hopes that there is an increase of 15% in customer orders for next year.How many workers will the manager need to have at the mill next year?


A) 10
B) 13
C) 16
D) 19

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The degree to which equipment,space,or labor is being used is commonly referred to as:


A) capacity.
B) output.
C) utilization.
D) cushion.

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

________ is the degree to which equipment,space,or labor is currently being used.

Correct Answer

verifed

verified

Give four principal reasons economies of scale can occur when output increases.Provide examples of each for a service firm.

Correct Answer

verifed

verified

The four reasons are spreading fixed cos...

View Answer

A standard work year is 2000 hours at the Luther Mill and it takes about an hour and a half to fill a customer order.Last year saw 15,000 customer orders at the mill and the manager has a new John Deere in mind as a company car,so he hopes that there is an increase of 15% in customer orders for next year.If the manager hires fourteen workers,what is the capacity cushion?


A) 7) 6%
B) 8) 2%
C) 6) 9%
D) 8) 8%

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

It takes a service rep an average of two minutes to take a customer's information.Over the course of a work week,the rep handles 160 calls a day during her eight hour shift.What is the service rep's capacity cushion?


A) 20%
B) 33%
C) 50%
D) 67%

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The ________ concept states that the average unit cost of a service or good can be reduced by increasing its output rate.

Correct Answer

verifed

verified

A planning horizon is defined as the period beyond which the company does not have customer orders.

A) True
B) False

Correct Answer

verifed

verified

What is a waiting line model,and what information can it provide?

Correct Answer

verifed

verified

Waiting line models use probab...

View Answer

Sleep Tight Motel has the opportunity to purchase an adjacent plot of land.Building on this land would increase their capacity from the current sales level of $515,000/year to $600,000/year.Sleep Tight experiences a 20 percent before-tax profit margin.It wishes to estimate the additional before-tax profits that the expansion will produce.Using the following information,how much more before-tax cash flow would be realized just in year 10 alone? Sleep Tight Motel has the opportunity to purchase an adjacent plot of land.Building on this land would increase their capacity from the current sales level of $515,000/year to $600,000/year.Sleep Tight experiences a 20 percent before-tax profit margin.It wishes to estimate the additional before-tax profits that the expansion will produce.Using the following information,how much more before-tax cash flow would be realized just in year 10 alone?   A) less than or equal to $20,000 B) greater than $20,000 but less than or equal to $25,000 C) greater than $25,000 but less than or equal to $30,000 D) greater than 30,000


A) less than or equal to $20,000
B) greater than $20,000 but less than or equal to $25,000
C) greater than $25,000 but less than or equal to $30,000
D) greater than 30,000

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

________ is the amount of reserve capacity that a firm maintains to handle a sudden increase in demand or temporary losses of production capacity.

Correct Answer

verifed

verified

________ occurs when the average cost per unit increases as the facility's size increases.

Correct Answer

verifed

verified

Diseconomi...

View Answer

Waiting line models are often used for capacity planning.

A) True
B) False

Correct Answer

verifed

verified