An activity that has more than one dependency arrow flowing into it is termed a(n)


A) Parallel activity.
B) Critical path.
C) Burst activity.
D) Merge activity.
E) Independent activity.

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity.

A) True
B) False

Correct Answer

verifed

verified

After the total slack for each activity is identified, the project manager can more easily identify the __________________.


A) Earned Value
B) Critical Path
C) Earliest Start Date
D) Total Project Slack

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

A _________ activity is one that has more than one activity taking place at the same time.


A) Burst
B) Merge
C) Parallel
D) None of these choices are correct.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

Which of the following represents an activity on an activity-on-node (AON) project network?


A) An arrow
B) A line
C) A node
D) Both an arrow and a line
E) An arrow, a line and a node all represent activities

F) B) and D)
G) All of the above

Correct Answer

verifed

verified

In developing a project network, neither looping nor conditional statements are permitted.

A) True
B) False

Correct Answer

verifed

verified

What is the Concurrent Engineering Approach and why should project managers be aware of it?

Correct Answer

verifed

verified

The chainlike sequence of finish-to-start relationships is replaced by a series of start-to-start lag relationships as soon as meaningful work can be initiated for the next phase.The resulting overlap of tasks slightly increases risk but results in a much shorter schedule.

The backward pass through a project network determines slack or how long an activity can be delayed without impacting the completion date of the project.

A) True
B) False

Correct Answer

verifed

verified

Activities which can take place at the same time are termed


A) Parallel activity.
B) Critical path.
C) Burst activity.
D) Merge activity.
E) Independent activity.

F) All of the above
G) B) and E)

Correct Answer

verifed

verified

When translated into a project network, a work package will become


A) A single activity.
B) One or more activities.
C) A milestone.
D) A critical path.
E) An arrow.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

B

A(n) _________ activity has more than one dependency arrow flowing from it.


A) Parallel
B) Critical path
C) Burst
D) Merge
E) Independent

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

How does the WBS differ from the project network? How are WBS and project networks linked?

Correct Answer

verifed

verified

The network is developed from the inform...

View Answer

Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).

A) True
B) False

Correct Answer

verifed

verified

What is a hammock activity and give an example?

Correct Answer

verifed

verified

A hammock activity identifies the use of...

View Answer

If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?


A) Start to Start
B) Start to Finish
C) Finish to Finish
D) Finish to Start
E) Any of these could be correct.

F) None of the above
G) C) and E)

Correct Answer

verifed

verified

A project network provides the basis for ________________________________ .


A) organizational authority
B) completing the effort on time and within budget
C) scheduling labor and equipment
D) None of these choices are correct.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

The critical path in a project network is the


A) Shortest path through the network.
B) Longest path through the network.
C) Network path with the most difficult activities.
D) Network path using the most resources.
E) Network path with the most merge activities.

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

B

The amount of delay within a task that will not delay the overall project is known as a


A) Total Slack.
B) Estimated Effort.
C) Opportunity Cost.
D) Both Total Slack and Opportunity Cost are correct.

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

________ activities must be completed immediately before a particular activity.


A) Merge
B) Burst
C) Predecessor
D) Successor
E) Parallel

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

The longest path through a project network is called the _________.

Correct Answer

verifed

verified

critical path
Explanation: The...

View Answer

Showing 1 - 20 of 105