Filters
Question type

Study Flashcards

The subjective approach to project analysis:


A) is used only when a firm has an all-equity capital structure.
B) uses the WACC of firm X as the basis for the discount rate for a project under consideration by firm Y.
C) assigns discount rates to projects based on the discretion of the senior managers of a firm.
D) allows managers to randomly adjust the discount rate assigned to a project once the project's beta has been determined.
E) applies a lower discount rate to projects that are financed totally with equity as compared to those that are partially financed with debt.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Explain how the use of internal equity rather than external equity affects the analysis of a project.

Correct Answer

verifed

verified

Internal equity avoids the flotation cos...

View Answer

Bleakly Enterprises has a capital structure of 55 percent common stock, 10 percent preferred stock, and 35 percent debt. The flotation costs are 4.5 percent for debt, 7 percent for preferred stock, and 9.5 percent for common stock. The corporate tax rate is 34 percent. What is the weighted average flotation cost?


A) 5.8 percent
B) 6.2 percent
C) 6.7 percent
D) 7.0 percent
E) 7.5 percent

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

Incorporating flotation costs into the analysis of a project will:


A) cause the project to be improperly evaluated.
B) increase the net present value of the project.
C) increase the project's rate of return.
D) increase the initial cash outflow of the project.
E) have no effect on the present value of the project.

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Markley and Stearns is a multi-divisional firm that uses its WACC as the discount rate for all proposed projects. Each division is in a separate line of business and each presents risks unique to those lines. Given this, a division within the firm will tend to:


A) receive less project funding if its line of business is riskier than that of the other divisions.
B) avoid risky projects so it can receive more project funding.
C) become less risky over time based on the projects that are accepted.
D) have equal probability of receiving funding as compared to the other divisions.
E) prefer higher risk projects over lower risk projects.

F) C) and E)
G) B) and E)

Correct Answer

verifed

verified

If a firm uses its WACC as the discount rate for all of the projects it undertakes then the firm will tend to: I. reject some positive net present value projects. II. accept some negative net present value projects. III. favor high risk projects over low risk projects. IV. increase its overall level of risk over time.


A) I and III only
B) III and IV only
C) I, II, and III only
D) I, II, and IV only
E) I, II, III, and IV

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

Silo Mills has a beta of 0.87 and a cost of equity of 11.9 percent. The risk-free rate of return is 2.8 percent. The firm is currently considering a project that has a beta of 1.03 and a project life of 6 years. What discount rate should be assigned to this project?


A) 13.33 percent.
B) 13.57 percent.
C) 13.62 percent.
D) 13.84 percent.
E) 14.09 percent.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

R.S. Green has 250,000 shares of common stock outstanding at a market price of $28 a share. Next year's annual dividend is expected to be $1.55 a share. The dividend growth rate is 2 percent. The firm also has 7,500 bonds outstanding with a face value of $1,000 per bond. The bonds carry a 7 percent coupon, pay interest semiannually, and mature in 7.5 years. The bonds are selling at 98 percent of face value. The company's tax rate is 34 percent. What is the firm's weighted average cost of capital?


A) 5.4 percent
B) 6.2 percent
C) 7.5 percent
D) 8.5 percent
E) 9.6 percent

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

The Bakery is considering a new project it considers to be a little riskier than its current operations. Thus, management has decided to add an additional 1.5 percent to the company's overall cost of capital when evaluating this project. The project has an initial cash outlay of $62,000 and projected cash inflows of $17,000 in year one, $28,000 in year two, and $30,000 in year three. The firm uses 25 percent debt and 75 percent common stock as its capital structure. The company's cost of equity is 15.5 percent while the aftertax cost of debt for the firm is 6.1 percent. What is the projected net present value of the new project?


A) -$6,208
B) -$5,964
C) -$2,308
D) $1,427
E) $1,573

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

What role does the weighted average cost of capital play when determining a project's cost of capital?

Correct Answer

verifed

verified

Assuming a project is equally as risky a...

View Answer

The pre-tax cost of debt:


A) is based on the current yield to maturity of the firm's outstanding bonds.
B) is equal to the coupon rate on the latest bonds issued by a firm.
C) is equivalent to the average current yield on all of a firm's outstanding bonds.
D) is based on the original yield to maturity on the latest bonds issued by a firm.
E) has to be estimated as it cannot be directly observed in the market.

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Delta Lighting has 30,000 shares of common stock outstanding at a market price of $17.50 a share. This stock was originally issued at $31 per share. The firm also has a bond issue outstanding with a total face value of $280,000 which is selling for 86 percent of par. The cost of equity is 16 percent while the aftertax cost of debt is 6.9 percent. The firm has a beta of 1.48 and a tax rate of 30 percent. What is the weighted average cost of capital?


A) 11.07 percent
B) 13.14 percent
C) 14.36 percent
D) 15.29 percent
E) 15.47 percent

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Textile Mills borrows money at a rate of 13.5 percent. This interest rate is referred to as the:


A) compound rate.
B) current yield.
C) cost of debt.
D) capital gains yield.
E) cost of capital.

F) All of the above
G) A) and C)

Correct Answer

verifed

verified

Suppose your company needs $14 million to build a new assembly line. Your target debt-equity ratio is 0.84. The flotation cost for new equity is 9.5 percent, but the floatation cost for debt is only 2.5 percent. What is the true cost of building the new assembly line after taking flotation costs into account?


A) 14.82 million
B) 14.94 million
C) 15.07 million
D) 15.12 million
E) 15.23 million

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

The Oil Derrick has an overall cost of equity of 13.6 percent and a beta of 1.28. The firm is financed solely with common stock. The risk-free rate of return is 3.4 percent. What is an appropriate cost of capital for a division within the firm that has an estimated beta of 1.18?


A) 12.37 percent
B) 12.41 percent
C) 12.54 percent
D) 12.67 percent
E) 12.80 percent

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The dividend growth model can be used to compute the cost of equity for a firm in which of the following situations? I. firms that have a 100 percent retention ratio II. firms that pay a constant dividend III. firms that pay an increasing dividend IV. firms that pay a decreasing dividend


A) I and II only
B) I and III only
C) II and III only
D) I, II, and III only
E) II, III, and IV only

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

The average of a firm's cost of equity and aftertax cost of debt that is weighted based on the firm's capital structure is called the:


A) reward to risk ratio.
B) weighted capital gains rate.
C) structured cost of capital.
D) subjective cost of capital.
E) weighted average cost of capital.

F) A) and C)
G) A) and D)

Correct Answer

verifed

verified

Which one of the following is the primary determinant of a firm's cost of capital?


A) debt-equity ratio
B) applicable tax rate
C) cost of equity
D) cost of debt
E) use of the funds

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

A firm's cost of capital:


A) will decrease as the risk level of the firm increases.
B) for a specific project is primarily dependent upon the source of the funds used for the project.
C) is independent of the firm's capital structure.
D) should be applied as the discount rate for any project considered by the firm.
E) depends upon how the funds raised are going to be spent.

F) D) and E)
G) A) and D)

Correct Answer

verifed

verified

Assigning discount rates to individual projects based on the risk level of each project:


A) may cause the firm's overall weighted average cost of capital to either increase or decrease over time.
B) will prevent the firm's overall cost of capital from changing over time.
C) will cause the firm's overall cost of capital to decrease over time.
D) decreases the value of the firm over time.
E) negates the firm's goal of creating the most value for the shareholders.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Showing 21 - 40 of 101

Related Exams

Show Answer