 What cost is the price of evaluating processes and their outputs to ensure that a project is error-free or within an acceptable error range?


A) prevention cost
B) appraisal cost
C) internal failure cost
D) external failure cost

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

 Which is a measure of quality control equal to one fault in one million opportunities problems?


A) ISO 9000
B) six 9s of quality rule
C) seven run rule
D) Six Sigma rule

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

 Which graphic display of data illustrates the results of a process over time?


A) statistical sampling chart
B) Pareto chart
C) Six Sigma chart
D) control chart

E) None of the above
F) All of the above

Correct Answer

verifed

verified

 Which addresses how well a product or service performs the customer's intended use?


A) reliability
B) performance
C) maintainability
D) functionality

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

 Which term is used when the project's processes and products meet written specifications?


A) conformance to requirements
B) fitness for use
C) project feasibility
D) benchmarking

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

 During which phase of the DMAIC process is the fishbone or Ishikawa diagram used?


A) define
B) measure
C) analyze
D) improve

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

 In the DMAIC process, the letter "C" stands for _____.

Correct Answer

verifed

verified

 Customer requirements are an important aspect of the quality planning process.

A) True
B) False

Correct Answer

verifed

verified

 _____ are groups of nonsupervisors and work leaders in a single company department who volunteer to conduct group studies on how to improve the effectiveness of work in their department.

Correct Answer

verifed

verified

 Integration testing involves testing of each individual component to ensure that it is as defect-free as possible.

A) True
B) False

Correct Answer

verifed

verified

 The _____ means taking responsibility for failures or not meeting quality expectations.

Correct Answer

verifed

verified

cost of no...

View Answer

 Describe the relationship between Six Sigma and statistics. What statistical concepts are involved in the Six Sigma philosophy?

Correct Answer

verifed

verified

An important concept in Six Sigma is imp...

View Answer

 What term is used for a bell-shaped curve that is symmetrical regarding the average value of the population (the data being analyzed) ?


A) skewed distribution
B) normal distribution
C) bimodal distribution
D) degenerate distribution

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

 List and briefly describe the three project quality management processes.

Correct Answer

verifed

verified

1. Planning quality management includes ...

View Answer

 _____ diagrams trace complaints about quality problems back to the responsible production operations.

Correct Answer

verifed

verified

Cause-and-...

View Answer

 Gantt charts cannot be used to aid project quality management.

A) True
B) False

Correct Answer

verifed

verified

 A run chart is a bar graph that depicts data points and their order of occurrence.

A) True
B) False

Correct Answer

verifed

verified

 Which system involves a three-part, continuous cycle of planning, controlling, and documenting quality in an organization?


A) Seven run rule
B) ISO 9000
C) Six Sigma
D) ASQ

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

 Which process helps integrate traditionally separate organizational functions, set process improvement goals and priorities, provide guidance for quality processes, and provide a point of reference for appraising current processes?


A) SQFD
B) MTBI
C) OPM3
D) CMMI

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

 Which statement is one of Juran's ten steps to quality improvement?


A) An organization should minimize top management involvement in the achievement of individual employee goals.
B) An organization should entrust improvement to individual employees rather than appointing teams or facilitators.
C) An organization should build awareness of the need and opportunity for improvement.
D) An organization should avoid "keeping score" in order to achieve an overall atmosphere of quality improvement.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified