Tasks in a WBS that are decomposed into smaller tasks are called _____ tasks.

Correct Answer

verifed

verified

Scope creep if not managed well can lead to the failure of information technology projects.

A) True
B) False

Correct Answer

verifed

verified

The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.

A) True
B) False

Correct Answer

verifed

verified

The _____ includes the approved project scope statement and its associated WBS and WBS dictionary.

Correct Answer

verifed

verified

_____ involves controlling changes to the project scope while keeping project goals and business strategy in mind.

Correct Answer

verifed

verified

_____ involves formal acceptance of the completed project scope by the stakeholders.


A) Scope validation
B) Scope planning
C) Scope control
D) Scope baseline

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The main tool for performing scope validation is _____ and group decision making techniques.

Correct Answer

verifed

verified

The ______ documents how project needs will be analyzed, documented, and managed.


A) requirements traceability matrix
B) requirements management plan
C) WBS
D) project scope statement

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

Correct Answer

verifed

verified

requirements traceab...

View Answer

List and briefly describe five approaches for creating work breakdown structures.

Correct Answer

verifed

verified

Using Guidelines
If guidelines for devel...

View Answer

_____ refers to the process of developing a working replica of the system or some aspect of the system.


A) Prototyping
B) Variance
C) Decomposition
D) Use case modeling

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

Project scope statements must include the project boundaries, constraints, and assumptions.

A) True
B) False

Correct Answer

verifed

verified

The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.

A) True
B) False

Correct Answer

verifed

verified

_____ involves developing a working replica of the system or some aspect of the system.

Correct Answer

verifed

verified

The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items.


A) analogy
B) bottom-up
C) top-down
D) mind mapping

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS.


A) analogy
B) bottom-up
C) top-down
D) mind mapping

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

A work package must always represent less than 80 hours of work.

A) True
B) False

Correct Answer

verifed

verified

A(n) _____ is a document that describes detailed information about each WBS item.

Correct Answer

verifed

verified

Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

A) True
B) False

Correct Answer

verifed

verified

_____ includes the processes involved in defining and controlling what work is or is not included in a project.

Correct Answer

verifed

verified

Project sc...