Large-scale capacity expansion with the expectation of high customer demand is called ________.

Correct Answer

verifed

verified

mass capac...

View Answer

The typical time horizon for Materials Requirements Planning (MRP) is


A) 6 months to 1 year.
B) up to 3 months.
C) weekly.
D) daily.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

A printer has been rated by the manufacturer to print 40 pages per minute (ppm) .However it is noticed that the printer has a 5% jamming rate,and also on average 20% of the time is lost on account of the operator loading the paper,aligning the print cartridge,etc.Thus,effectively the printer can print how many pages per minute (ppm) ?


A) 30.4
B) 36
C) 28.8
D) 24.6

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Increasing the capacity of the operation just before a bottleneck operation will increase the output of the process.

A) True
B) False

Correct Answer

verifed

verified

The capacity strategy where capacity is increased at relatively the same rate that demand increases is called ________.

Correct Answer

verifed

verified

Breaking product families into individual products and components of products is called ________.

Correct Answer

verifed

verified

Creating a high-level planning,which involves groups or families of products is called


A) group planning.
B) aggregation.
C) master scheduling.
D) enterprise planning.

E) C) and D)
F) A) and C)

Correct Answer

verifed

verified

The feasibility check of a Materials Requirement Plan (MRP) is


A) rough-cut capacity planning (RCCP) .
B) the aggregate capacity plan.
C) the detailed capacity plan.
D) enterprise capacity plan.

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

Efficiency is the ratio of actual output to design capacity.

A) True
B) False

Correct Answer

verifed

verified

Inventory information for firm Best Tools:  Unventory at  the end of  March: 200 units  Expected  demand  during April: 50 units  Production  planned for  April: 100 units \begin{array} { l | l } \text { Unventory at } & \\\text { the end of } & \\\text { March: } & 200 \text { units } \\\hline \text { Expected } & \\\text { demand } & \\\text { during April: } & 50 \text { units } \\\hline \text { Production } & \\\text { planned for } & \\\text { April: } & 100 \text { units }\end{array} What is the expected inventory at the end of April?


A) 50 units
B) 150 units
C) 250 units
D) 350 units

E) All of the above
F) A) and B)

Correct Answer

verifed

verified