A) Labor rate variance.
B) Labor efficiency variance.
C) Labor usage variance.
D) Labor direct variance.
Correct Answer
verified
Multiple Choice
A) The company paid the workers overtime.
B) The company hired more experienced workers.
C) The company purchased materials that were hard to work with.
D) The workers "goofed around" and wasted time.
Correct Answer
verified
Multiple Choice
A) Zero.
B) Favorable.
C) Unfavorable.
D) Either favorable or unfavorable depending on the budgeted overhead.
Correct Answer
verified
Multiple Choice
A) $1,200 favorable
B) $1,800 unfavorable
C) $3,000 favorable
D) $1,200 unfavorable
Correct Answer
verified
Multiple Choice
A) $129,500.
B) $128,000.
C) $130,000.
D) $130,500.
Correct Answer
verified
Multiple Choice
A) Factory overhead costs incurred were greater than standard costs charged to production.
B) The plant was operated at less than normal capacity.
C) Factory overhead costs incurred were less than standard costs charged to production.
D) Factory overhead costs incurred were unreasonably large in relation to units produced.
Correct Answer
verified
Multiple Choice
A) Underapplied or overapplied variable cost element of overhead.
B) Underapplied or overapplied fixed cost element of overhead.
C) Difference in budgeted costs and actual costs of fixed overhead items.
D) Difference in budgeted costs and actual costs of variable overhead items.
Correct Answer
verified
Multiple Choice
A) $187.50 favorable
B) $187.50 unfavorable
C) $437.50 favorable
D) $437.50 unfavorable
Correct Answer
verified
Multiple Choice
A) Actual price by the difference between actual quantity purchased and standard quantity used.
B) Actual quantity purchased by the difference between actual price and standard price.
C) Standard price by the difference between standard quantity purchased and standard quantity used.
D) Standard quantity purchased by the difference between actual price and standard price.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) $390 favorable
B) $390 unfavorable
C) $400 favorable
D) $400 unfavorable
Correct Answer
verified
Multiple Choice
A) $6,500 favorable
B) $6,400 unfavorable
C) $1,800 favorable
D) $6,400 favorable
Correct Answer
verified
Multiple Choice
A) Ignoring the cause of favorable variances.
B) Revising the standard because it was set incorrectly.
C) Improving the manufacturing process.
D) Looking for new suppliers.
Correct Answer
verified
Multiple Choice
A) $1,200 unfavorable
B) $200 unfavorable
C) $1,000 favorable
D) $200 favorable
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) $2,800 unfavorable
B) $1,900 unfavorable
C) $4,600 unfavorable
D) $1,800 unfavorable
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) When material is purchased
B) When material is used in production
C) When purchase order is originated
D) When material is issued
Correct Answer
verified
Multiple Choice
A) Reclassified to deferred charges until all related production is sold
B) Closed to cost of goods sold in the period in which they arose
C) Allocated among cost of goods manufactured and ending work in process inventory
D) Capitalized as a cost of ending finished goods inventory
Correct Answer
verified
Multiple Choice
A) Can be achieved only under the most efficient operating conditions.
B) Is high enough to provide motivation and promote efficiency, but is still attainable.
C) Makes no allowance for normal was or spoilage.
D) None of these is correct.
Correct Answer
verified
Showing 41 - 60 of 75
Related Exams