Filters
Question type

Study Flashcards

The investigation of a materials quantity variance usually begins in the


A) production department.
B) purchasing department.
C) sales department.
D) controller's department.

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

The direct materials quantity standard would not be expressed in


A) pounds.
B) barrels.
C) dollars.
D) board feet.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A company uses 8,400 pounds of materials and exceeds the standard by 300 pounds. The quantity variance is $1,800 unfavorable. What is the standard price?


A) $2
B) $4
C) $6
D) Cannot be determined from the data provided.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Denmark Corporation's variance report for the purchasing department reports 1,000 units of material A purchased and 2,400 units of material B purchased. It also reports standard prices of $2 for Material A and $3 for Material B. Actual prices reported are $2.10 for Material A and $2.80 for Material B. Denmark should report a total price variance of


A) $380 F.
B) $340 F.
C) $340 U.
D) $380 U.

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

Which of the following is true?


A) The form, content, and frequency of variance reports vary considerably among companies.
B) The form, content, and frequency of variance reports do not vary among companies.
C) The form and content of variance reports vary considerably among companies, but the frequency is always weekly.
D) The form and content of variance reports are consistent among companies, but the frequency varies.

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

The standard predetermined overhead rate used in setting the standard overhead cost is determined by dividing


A) budgeted overhead costs by an expected standard activity index.
B) actual overhead costs by an expected standard activity index.
C) budgeted overhead costs by actual activity.
D) actual overhead costs by actual activity.

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The total materials variance is equal to the


A) materials price variance.
B) difference between the materials price variance and materials quantity variance.
C) product of the materials price variance and the materials quantity variance.
D) sum of the materials price variance and the materials quantity variance.

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

The formula for the materials price variance is


A) (AQ × SP) - (SQ × SP) .
B) (AQ × AP) - (AQ × SP) .
C) (AQ × AP) - (SQ × SP) .
D) (AQ × SP) - (SQ × AP) .

E) C) and D)
F) A) and C)

Correct Answer

verifed

verified

The total overhead variance is the difference between actual overhead costs and overhead costs applied to work done.

A) True
B) False

Correct Answer

verifed

verified

If the materials price variance is $3,600 F and the materials quantity and labor variances are each $2,700 U, what is the total materials variance?


A) $3,600 F
B) $2,700 U
C) $900 F
D) $4,050 U

E) All of the above
F) A) and C)

Correct Answer

verifed

verified

Unfavorable materials price and quantity variances are generally the responsibility of the \quad\quad\quad\quad Price \quad\quad\quad\quad\quad\quad Quantity a. Purchasing department \quad\quad Purchasing Department b. Purchasing department \quad\quad Production Department c. Production department \quad\quad Production Department d. Production Department \quad\quad Purchasing Department

Correct Answer

verifed

verified

The difference between a budget and a standard is that


A) a budget expresses what costs were, while a standard expresses what costs should be.
B) a budget expresses management's plans, while a standard reflects what actually happened.
C) a budget expresses a total amount, while a standard expresses a unit amount.
D) standards are excluded from the cost accounting system, whereas budgets are generally incorporated into the cost accounting system.

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

The difference between the actual labor rate multiplied by the actual labor hours worked and the standard labor rate multiplied by the standard labor hours is the


A) total labor variance.
B) labor price variance.
C) labor quantity variance.
D) labor efficiency variance.

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

The purchasing agent of the Poplin, Inc. ordered materials of lower quality in an effort to economize on price. What variance will most likely result?


A) Favorable materials quantity variance
B) Favorable total materials variance
C) Unfavorable materials price variance
D) Unfavorable labor quantity variance

E) B) and C)
F) B) and D)

Correct Answer

verifed

verified

Using standard costs


A) can make management planning more difficult.
B) promotes greater economy.
C) does not help in setting prices.
D) weakens management control.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The investigation of materials price variance usually begins in the


A) first production department.
B) purchasing department.
C) controller's office.
D) accounts payable department.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

There could be instances where the production department is responsible for a direct materials price variance.

A) True
B) False

Correct Answer

verifed

verified

The two levels that standards may be set at are


A) normal and fully efficient.
B) normal and ideal.
C) ideal and less efficient.
D) fully efficient and fully effective.

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

Budget data are not journalized in cost accounting systems with the exception of


A) the application of manufacturing overhead.
B) direct labor budgets.
C) direct materials budgets.
D) cash budget data.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Shipp, Inc. manufactures a product requiring two pounds of direct material. During 2016, Shipp purchases 24,000 pounds of material for $99,200 when the standard price per pound is $4. During 2016, Shipp uses 22,000 pounds to make 12,000 products. The standard direct material cost per unit of finished product is


A) $8.27.
B) $9.01.
C) $8.00.
D) $8.53.

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

Showing 41 - 60 of 161

Related Exams

Show Answer